Question: Apply Critical Path Method for the given the Network Diagram. Provide your answer, below. A. Identify the all the available paths. B. Calculate the

Apply Critical Path Method for the given the Network Diagram. Provide your answer, below. A. Identify the all the available paths. B. Calculate the duration for each path. C. Highlight the critical path of the project chart. D=8 2 5 A=3 H=2 E=6 B=4 J=1 3 7 8 F=4 C=7 1=3 4 6 G=4 Path Path Identification Duration Calculation Duration CP() 1 ACTIVITIES 2 3 4 D. Also, draw the project Gantt chart. A D E am 0 - - - F G H I J 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 DAYS
Step by Step Solution
There are 3 Steps involved in it
To apply the Critical Path Method CPM for the given network diagram lets follow the steps A B and C A Identify all the available paths Starting with t... View full answer