Question: Using the following data, enter the various tasks and create a Gantt chart using MSProject. Assign the individuals responsible for each activity, and once you
.png)
Activitv A. Research product B. Interview customers C. Design survey D. Collect data Duration Predecessors Resource Tom Allen Liz Watts Rich Watkins Gary Sims % Complete 100 75 50 4 4 B, C
Step by Step Solution
3.45 Rating (177 Votes )
There are 3 Steps involved in it
Microsoft product screen shots reprinted with permission from Microsoft Corpo... View full answer