Question: As a new Project Manager assigned to this project, you are required to execute this project and deliver based on the criteria provided: 1. Log

As a new Project Manager assigned to this project, you are required to execute this project and

deliver based on the criteria provided:

1. Log on to Project Team Builder Training Simulator with your own credentials.

2. Go to Project Team Builder: Use Cases / Folder: medium /File: Medium Radar Development.scn

3. Complete the simulation.

Once you have completed your project generate the PTB Simulation Report and use it to submit a

Final Project Status Report.

Three files must be submitted as part of this status report: The PTB Simulation Report, Microsoft Project file, PowerPoint file showing:

Resource Charts (Engineers)

Resource Chart (Technicians)

Detailed Budget

Gantt Chart

The Lean Indicator

Identify 2 risk events related to this project

Answer the following:

Changes have been applied to Task Receiver Design. It has now the following modes:

Mode name Optimistic Duration Most Likely Duration Pessimistic Duration
Reengineer 8 9 10
New Design 7 8 15
Consultant R 9 12 15

Calculate the modes duration based on three-point estimate method.

Which mode do you recommend based on the three-point estimate method?

Will you be able to meet the Target Period?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!