Question: As a new Project Manager assigned to this project, you are required to execute this project and deliver based on the criteria provided: 1. Log
As a new Project Manager assigned to this project, you are required to execute this project and
deliver based on the criteria provided:
1. Log on to Project Team Builder Training Simulator with your own credentials.
2. Go to Project Team Builder: Use Cases / Folder: medium /File: Medium Radar Development.scn
3. Complete the simulation.
Once you have completed your project generate the PTB Simulation Report and use it to submit a
Final Project Status Report.
Three files must be submitted as part of this status report: The PTB Simulation Report, Microsoft Project file, PowerPoint file showing:
Resource Charts (Engineers)
Resource Chart (Technicians)
Detailed Budget
Gantt Chart
The Lean Indicator
Identify 2 risk events related to this project
Answer the following:
Changes have been applied to Task Receiver Design. It has now the following modes:
| Mode name | Optimistic Duration | Most Likely Duration | Pessimistic Duration |
| Reengineer | 8 | 9 | 10 |
| New Design | 7 | 8 | 15 |
| Consultant R | 9 | 12 | 15 |
Calculate the modes duration based on three-point estimate method.
Which mode do you recommend based on the three-point estimate method?
Will you be able to meet the Target Period?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts