Question: As a new project manager, you are learning the differences between projects and routine work. You are tasked with managing a project to develop a

As a new project manager, you are learning the differences between projects and routine work. You are tasked with managing a project to develop a new product for your company. Which of the following characteristics best defines your task as a project?
The task is part of daily operational activities.
The task has a unique goal with a specific end date.
The task involves routine maintenance of existing products.
The task involves ongoing customer support.