Question: As a project manager, you are tasked with a project that will manufacture a camera lens for a new Earth imaging satellite. Your project team
As a project manager, you are tasked with a project that will manufacture a camera lens for a new Earth imaging satellite. Your project team has completed manufacturing and testing, fulfilling all requirements. Your final project deliverable meets the acceptance criteria and has been formally signed off and approved by the customer. Which process has just been completed?
Group of answer choices
Close Project/ Project Phase.
Control Scope.
Validate Scope.
Perform Integrated Change Control.