Question: As a project manager, you are tasked with a project that will manufacture a camera lens for a new Earth imaging satellite. Your project team

As a project manager, you are tasked with a project that will manufacture a camera lens for a new Earth imaging satellite. Your project team had multiple facilitated workshops and was able to define the scope of the project. Which of the following techniques could be used to create a WBS for this project that will include work packages such as curving the lens, etc.?

Group of answer choices

Product Analysis.

Decomposition.

Benchmarking.

Variance Analysis.