Question: As a project manager, you assign someone as responsible on a RACl chart. What do you expect them to do on the project? Learn about

As a project manager, you assign someone as responsible on a RACl chart. What do you expect them to do on the project?
Learn about tasks when they are complete
Give feedback according to their subject matter expertise
Carry out the work to complete the tasks
Ensure the work gets completed