Question: Question 8 As a project manager, you assign someone as informed on a RACI chart. What do you expect them to do on the project?
Question
As a project manager, you assign someone as informed on a RACI chart. What do you expect them to do on the project?
point
Learn about the final decision on the project
Give feedback according to their subject matter expertise
Ensure the work gets completed
Carry out the work to complete the tasks