Question: As per the project plan, your project will have a very short regression testing phase. Foreseeing a risk, your lead asks you and your team
As per the project plan, your project will have a very short regression testing phase. Foreseeing a risk, your lead asks you and your team to prioritize the test cases as and when you create so that the prioritized test cases can be executed first during regression. Do you think that this prioritization will help in doing regression?
Select one:
a No only a schedule extension or increase in resources can help this situation.
b No an adhoc or random testing should help this situation better.
c Yes, the prioritized test suite can better meet the objective than would an ad hoc or random ordering of test cases.
d Yes, the prioritized test suite would result in a complete fault detection saving cost and time.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock