As the project manager on the high-rise project, there have been a lot of fluctuations in the schedule from week to week and you are trying to identify a trend as to where the project stands. What tool is useful in identifying trends in the project from period to period?
Group of answer choices
Executive Summary
Look ahead schedule
Schedule Maintenance Log
Schedule Summary