Question: Assignment 1: Activity Predecessor Normal Duration Crash Duration Normal Cost Additional Costday of Activity ($) to Crash ($) 0 2 2 1.200 B A 5

Assignment 1: Activity Predecessor Normal

Assignment 1: Activity Predecessor Normal Duration Crash Duration Normal Cost Additional Costday of Activity ($) to Crash ($) 0 2 2 1.200 B A 5 4 1,800 600 B 6 4 1,700 400 D B 7 5 1,500 700 E 4 3 CD 1,900 500 1. What are the critical path and the estimated completion time? 2. Find the best schedule and the final total project cost