Question: Assignment 4: Project Overhead Cost: S600/day Activity Predecessor Normal Duration Crash Normal Cost Additional Costday Duration of Activity ($) to Crash (5) 2 2 1,200

Assignment 4: Project Overhead Cost: S600/day

Assignment 4: Project Overhead Cost: S600/day Activity Predecessor Normal Duration Crash Normal Cost Additional Costday Duration of Activity ($) to Crash (5) 2 2 1,200 0 A 1,800 600 B 6 4 1,700 400 B 5 4 D B 7 5 1,500 700 E CD 4 3 1,900 500 1. What are the critical path and the estimated completion time? 2. Determine slacks for all activities 3. Find the best schedule and the final total project cost