Question: Project Overhead cost $600/day Activity Predecessor Normal Duration Crash Duration Crash Cost per Normal Cost Day A N 2 1,200 B A 5 4 1,800

Project Overhead cost $600/day Activity
Project Overhead cost $600/day Activity Predecessor Normal Duration Crash Duration Crash Cost per Normal Cost Day A N 2 1,200 B A 5 4 1,800 600 B 6 4 1,700 400 D B 7 5 1,500 700 E CD 4 3 1.900 500 1. What is the duration for the project for the lowest total cost? 2. What is the shortest duraton possible for this project? What is the total cost for the shortest duration