Question: Assignment 2 B B 8 D E 6 G D 10 Preceding Activity Activity Description of work Activity Time Drawings Dev. None 5 Approval 10

Assignment 2 B B 8 D E 6 G D 10 Preceding

Assignment 2 B B 8 D E 6 G D 10 Preceding Activity Activity Description of work Activity Time Drawings Dev. None 5 Approval 10 Master Plan Flooring 12 Wall installtion F Ceiling 12 Progress Report Documentation E&F 1 Completion G&H Instruction: Develop a project network from the above table and answer the following questions 1. What is the entire project length? 2. How many critical paths? 3. List all the critical paths. 4. How many 'slack' days in activity E? 5. How many days for early finish (EF) in activity G? 30 20

Step by Step Solution

There are 3 Steps involved in it