Question: Bakersfield Pools is about to work on a project to install a backyard pool and build an accompanying bathhouse. The installation process is fairly well
Bakersfield Pools is about to work on a project to install a backyard pool and build an accompanying bathhouse. The installation process is fairly well defined. Building the pool involves digging the foundation, pouring concrete, and ordering and installing a filtration system. The bathhouse work involves constructing the bathhouse, installing the additional required plumbing, and installing the necessary electrical work. The process is shown in the table below.
tableActivityDescription,tableImmediatePredecessorsDurationADig pool foundation,BOrder filtration system,CReceive filtration system,BDPour concrete,AEInstall filtration system,C DFConstruct bathhouse,GInstall electrical wiring,FHInstall plumbing,FIConnect water supply,HJTest,E G I,
Answer the following questions. Ignore the possibility of crashing until part f
a Draw the network diagram for the project. Calculate early start, early finish, late start, late finish, and slack times.
b Bakersfield Pools works all days a week. The customer wants this pool completed in time for a birthday party in days. Can it be done? Why or why not? Note: this means the entire project must be completed. Crashing is NOT possible at this point.
c The staff member who is in charge of pouring concrete wants to go on a twoweek vacation starting in days. Can Bakersfield Pools let him go when he wants? Why or why not?
d Equipment required to do task the installation of the filtration system is currently undergoing repairs. Until it is repaired, no work can be done on task What is the latest day those repairs can be completed by without delaying the project? Give your reasoning. AD please
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock