Question: Assignment i Saved From the following information, develop an AON project network. Complete the forward and backward and identify the critical path. How many days

Assignment i Saved From the following information, develop an AON project network. Complete the forward and backward and identify the critical path. How many days will the project take? ID Description Survey site Excavate site Install power lines Install drainage Pour foundation Predecessor None B C D Time 4 5 2 Vow 3 4 14 days. es The project will take The critical path is The late start on Activity C is The slack on Activity C is The slack on Activity D is The early start on Activity E is days. days. days. days. Prev 1 of 31 Next > OCX w 20220222_204128.jpg HW3 (Due date F....docx Chapter 1 Lecture....pptx