Question: From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many
From the following information, develop an AON project network. Complete the forward and
backward pass, compute activity slack, and identify the critical path. How many days will the
project take?

6.6. From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take? ID Description Predecessor Time A Survey site None 2 B Excavate site A 4 C Install power lines B D Install drainage B UI E Pour foundation C. D W itly clear