Question: Given the following project -Draw the diagram and determine the ES, EF, LS, and LF, slack and critical path. You will need this information for
Given the following project
-Draw the diagram and determine the ES, EF, LS, and LF, slack and critical path. You will need this information for the questions.
-How long will the project take?
-What is the ES, EF, LS and LF for activities D and F?
-What activities have slack and how much slack do they have?
-What is the critical path?
Given the following project Immediate Activity Predecessor Time (wks) A 2 D 51 D. E 4 Draw the diagram and determine the ES, EF LS, and LF. slack and critical path You will need this information tfor all the questions How kong will the project take
Step by Step Solution
3.49 Rating (172 Votes )
There are 3 Steps involved in it
Explanation Activity on Node network diagram Forward Pass Earliest Start ... View full answer