Question: Given the following project network: a. Identify the critical path and earliest start and finish for each task. b. Calculate slack for every project activity.
Given the following project network:
a. Identify the critical path and earliest start and finish for each task.
b. Calculate slack for every project activity.
c. Draw this network as a Gantt chart.
Step by Step Solution
3.41 Rating (170 Votes )
There are 3 Steps involved in it
a Critical path is A C D F b The slack for activity E is 7 an... View full answer