Question: Assume a project information is given in the table below: Activity Immediate Predecessor Duration (Days) A --- 5 B --- 5 C --- 5 D

Assume a project information is given in the table below:

Activity Immediate Predecessor Duration (Days)
A --- 5
B --- 5
C --- 5
D A, B 4
E B 3
F C 8
G D,E 6

  1. Which of the followings show all of the critical activities and total duration of the project?
  2. Which of the followings show the Earliest Start (ES) time of activity G?
  3. Which of the followings show the Earliest Start (ES) time of activity F?
  4. Which of the followings show the Latest Start (LS) time of activity G?
  5. Which of the followings show the Latest Start (LS) time of activity F?
  6. Which of the followings show the Latest Start (LS) time of activity E?
  7. Which of the followings show the Earliest Finish (EF) time of activity E?
  8. Which of the followings show the Earliest Finish (EF) time of activity F?
  9. Which of the followings show the Latest Finish (LF) time of activity E?
  10. Which of the followings show the Latest Finish (LF) time of activity F?
  11. Which of the followings show the Slack (S) time of activity E?
  12. Which of the followings show the Slack (S) time of activity F?
  13. What is the minimum number of activities that have to be delayed for the project to get delayed?
  14. What is the minimum number of non-critical activities that have to be delayed for the project to get delayed?
  15. What is the maximum number of activities that can be delayed for the project not to get delayed?
  16. What is the maximum number of activities that can be delayed for the project not to have additional critical activities?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!