Question: Assume a project information is given in the table below: Activity Immediate Predecessor Duration (Days) A --- 5 B --- 5 C --- 5 D
Assume a project information is given in the table below:
| Activity | Immediate Predecessor | Duration (Days) |
|---|---|---|
| A | --- | 5 |
| B | --- | 5 |
| C | --- | 5 |
| D | A, B | 4 |
| E | B | 3 |
| F | C | 8 |
| G | D,E | 6 |
- Which of the followings show all of the critical activities and total duration of the project?
- Which of the followings show the Earliest Start (ES) time of activity G?
- Which of the followings show the Earliest Start (ES) time of activity F?
- Which of the followings show the Latest Start (LS) time of activity G?
- Which of the followings show the Latest Start (LS) time of activity F?
- Which of the followings show the Latest Start (LS) time of activity E?
- Which of the followings show the Earliest Finish (EF) time of activity E?
- Which of the followings show the Earliest Finish (EF) time of activity F?
- Which of the followings show the Latest Finish (LF) time of activity E?
- Which of the followings show the Latest Finish (LF) time of activity F?
- Which of the followings show the Slack (S) time of activity E?
- Which of the followings show the Slack (S) time of activity F?
- What is the minimum number of activities that have to be delayed for the project to get delayed?
- What is the minimum number of non-critical activities that have to be delayed for the project to get delayed?
- What is the maximum number of activities that can be delayed for the project not to get delayed?
- What is the maximum number of activities that can be delayed for the project not to have additional critical activities?
Step by Step Solution
There are 3 Steps involved in it