Question: Assume a project information is given in the table below: Activity Immediate Processor Duration (Days) A --- 5 B --- 5 C --- 5 D

Assume a project information is given in the table below:

Activity Immediate Processor Duration (Days)
A --- 5
B --- 5
C --- 5
D A, B 4
E B 3
F C 8
G D, E 6

  1. What is the minimum number of activities that have to be delayed for the project to get delayed?
  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. None of the above (What is your answer?)
  1. What is the minimum number of non-critical activities that have to be delayed for the project to get delayed?
  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. None of the above (What is your answer?)
  1. What is the maximum number of activities that can be delayed for the project not to get delayed?
  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. None of the above (What is your answer?)
  1. What is the maximum number of activities that can be delayed for the project not to have additional critical activities?

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. None of the above (What is your answer?)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!