Question: Assume aggressive duration. Creat Gantt chart by doubling the durations and assume multitasking is ok. 19. Refer to Figure 8.22. Scheduling Activity T before Activity
19. Refer to Figure 8.22. Scheduling Activity T before Activity Q would also have resolved the resource contingency. Explain why this alternative was not selected. 20. Consider the data about project activities given in the table subsequently. Create the Gantt chart. Schedule the work in such a way that each person always bas only one task to perform (do not reduce the durations of activities or insert buffers as yet). Indicate the critical chain. Coette Gunt chart by doubling the duretions and c. Indicate where the feeding buffers should be inserted. d. What is the difference in the lengths of the critical path and the critical chain? is ok