Question: Assume that Systems Analysis actually finished at 8 weeks, Design Input & Output actually finished at 1 5 weeks, and Design Database actually finished at
Assume that Systems Analysis actually finished at weeks, Design Input & Output actually finished at weeks, and Design Database actually finished at weeks. Recalculate the expected project completion time in the table below.
Activity ED ES EF LS LF TS AF
Prob. Def.
Sys Analysis
Design IO
Design DB
Dev. Input
Dev. Output
Dev. DB
Test System
Implement
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock