Question: Assume that Systems Analysis actually finished at 8 weeks, Design Input & Output actually finished at 1 5 weeks, and Design Database actually finished at

Assume that Systems Analysis actually finished at 8 weeks, Design Input & Output actually finished at 15 weeks, and Design Database actually finished at 19 weeks. Recalculate the expected project completion time in the table below.
Activity ED ES EF LS LF TS AF
1. Prob. Def.
2. Sys. Analysis 8
3. Design I/O 15
4. Design DB 19
5. Dev. Input
6. Dev. Output
7. Dev. DB
8. Test System
9. Implement

Step by Step Solution