Question: Assume that the activity time estimates ( in days ) for the swimming pool construction project are as follows: table [ [ Activity ,

Assume that the activity time estimates (in days) for the swimming pool construction project are as follows:
\table[[Activity,Optimistic,Most Probable,Pessimistic],[A,3,5,6],[B,2,4,6],[C,5,6,7],[D,7,9,10],[E,2,4,6],[F,1,2,3],[G,5,8,10],[H,6,8,10],[I,3,4,5]]
a. What are the critical activities? If necessary, round your answers to two decimal places. If your answer is zero, enter "0".
\table[[Activity,Expected Time,Variance],[A,,],[B,,],[C,,],[D,,],[E,,],[F,,],[G,,],[H,,],[I,,]]