Question: Assume that you apply the double sampling plan n1-200, c1-5, n2-300, c2=7 for the lots N=2000. LTPD=5% and AQL=2% A) Calculate the producer's risk.

Assume that you apply the double sampling plan n1-200, c1-5, n2-300, c2=7

 

Assume that you apply the double sampling plan n1-200, c1-5, n2-300, c2=7 for the lots N=2000. LTPD=5% and AQL=2% A) Calculate the producer's risk. B) Calculate the ASN using AQL. C) Calculate the rejection probability after the second sample using AQL.