Question: Assume the following information: Queue time Wait time Process time Move time Hours 32 ? 2 2 ? GN NG Inspection time If the delivery

Assume the following information: Queue time Wait time Process time Move time Hours 32 ? 2 2 ? GN NG Inspection time If the delivery cycle time is 63 hours and the manufacturing cycle efficiency (MCE) is 0.05, then the wait time is closest to: Multiple Choice 13 hours. 17 hours. 23 hours. 21 hours
Step by Step Solution
There are 3 Steps involved in it