Question: LIRDILAR Assume the following information: Queue time Wait time Process time Move time Inspection time Hours 32 24 2 2 4 The throughput time (manufacturing
LIRDILAR Assume the following information: Queue time Wait time Process time Move time Inspection time Hours 32 24 2 2 4 The throughput time (manufacturing cycle time) is: Multiple Choice 62 hours. 28 hours. 40 hours