Question: Assume the following information: Queue time Wait time Process time Move time Inspection time Hours 30 24 2 2 4 The throughput time (manufacturing cycle

 Assume the following information: Queue time Wait time Process time Move
time Inspection time Hours 30 24 2 2 4 The throughput time

Assume the following information: Queue time Wait time Process time Move time Inspection time Hours 30 24 2 2 4 The throughput time (manufacturing cycle time) is: Multiple Choice O 62 hours. O 60 hours. 38 hours. O 26 hours. O