Question: Assume the network and data that follow: ACTIVITY NORMAL TIME ( WEEKS ) NORMAL COST CRASH TIME ( WEEKS ) CRASH COST IMMEDIATE PREDECESSORS A
Assume the network and data that follow:
ACTIVITY NORMAL TIME WEEKS NORMAL COST CRASH TIME WEEKS CRASH COST IMMEDIATE PREDECESSORS
A $ $
B A
C A
D A
E B
F D
G C E F
b Indicate the critical path when normal activity times are used.
multiple choice
ABEG
ADEG
ACFG
ADFG
c Demonstrate the crashing steps needed to minimize the cost of crashing down to various project lengths. Consider project lengths of and weeks. For each possible step down in project length, specify which activity would be crashed to achieve that length, compute the resultant length of each path in the project, and compute the crashing costs as shown in the table below.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock