Question: Assume the network and data that follow: ACTIVITY NORMAL TIME (WEEKS) NORMAL COST CRASH TIME (WEEKS) CRASH COST IMMEDIATE PREDECESSORS A 4 $ 30 3
Assume the network and data that follow:
| ACTIVITY | NORMAL TIME (WEEKS) | NORMAL COST | CRASH TIME (WEEKS) | CRASH COST | IMMEDIATE PREDECESSORS | ||||
| A | 4 | $ | 30 | 3 | $ | 35 | |||
| B | 7 | 100 | 3 | 140 | A | ||||
| C | 8 | 60 | 5 | 150 | A | ||||
| D | 6 | 110 | 5 | 170 | A | ||||
| E | 4 | 90 | 2 | 130 | B | ||||
| F | 3 | 70 | 2 | 100 | D | ||||
| G | 6 | 50 | 5 | 120 | C, E, F | ||||
b. Indicate the critical path when normal activity times are used.
| A-B-E-G | |
| A-C-F-G | |
| A-D-F-G | |
| A-D-E-G |
c. Compute the minimum total direct cost for each project duration based on the cost associated with each activity. Consider durations of 16, 17, 18, 19, 20, and 21 weeks. (Leave no cells blank - be certain to enter "0" wherever required.
| ABEG | |||||||
| Length of path | ACG | ||||||
| ADFG | |||||||
| Activity crashed | |||||||
| Crash cost | |||||||
| Cum. crash cost | |||||||
| Total direct cost | |||||||