Question: Problem 5-20 Assume the network and data that follow: ACTIVITY NORMAL TIME (WEEKS) NORMAL COST CRASH TIME (WEEKS) CRASH COST IMMEDIATE PREDECESSORS A 4 $

Problem 5-20

Assume the network and data that follow:

ACTIVITY NORMAL TIME (WEEKS) NORMAL COST CRASH TIME (WEEKS) CRASH COST IMMEDIATE PREDECESSORS
A 4 $ 40 3 $ 60
B 3 90 1 140 A
C 7 60 4 90 A
D 6 120 5 130 A
E 5 110 3 160 B
F 7 70 5 100 D
G 4 80 3 120 C, E, F

b. Indicate the critical path when normal activity times are used.

A-D-E-G
A-B-E-G
A-C-F-G
A-D-F-G

c. Compute the minimum total direct cost for each project duration based on the cost associated with each activity. Consider durations of 16, 17, 18, 19, 20, and 21 weeks. (Leave no cells blank - be certain to enter "0" wherever required.

ABEG
Length of path ACG
ADFG
Activity crashed (Click to select)DGAFE & FNone (Click to select)ANoneGE & FFD (Click to select)E & FDANoneFG (Click to select)GFNoneDE & FF (Click to select)DFE & FAANone (Click to select)ADFNoneGG
Crash cost
Cum. crash cost
Total direct cost

d-1. If the indirect costs for each project duration are $400 (21 weeks), $350 (20 weeks), $300 (19 weeks), $250 (18 weeks), $200 (17 weeks), and $150 (16 weeks), what is the total project cost for each duration?+

Duration Total Costs
21 $
20
19
18
17
16

d-2. Indicate the minimum total project cost duration.

16 weeks
17 weeks
13 weeks
14 or 15 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!