Question: Assume the overhead costs for this project are $ 2 , 5 0 0 / month . Also, a penalty of $ 1 0 ,

Assume the overhead costs for this project are $2,500/month. Also, a penalty of $10,000
is assessed for each month the project is delayed beyond month 25. What is the optimal
crashing strategy? What is the net benefit of the optimal crashing strategy? Please
describe your crashing strategy step-by-step.
c. What is the optimal project duration? What are the critical paths as a result of your
crashing?