Question: Assume you are working with your project team to develop a Work Breakdown Structure ( WBS ) for a home construction project ( Figure 1
Assume you are working with your project team to develop a Work Breakdown Structure WBS for a home construction project Figure WBS for Home Construction Project Your team has elected to proceed with a hardware, product oriented
approach to develop the level components. Which of the following includes appropriate components to define level of your WBS
Group of answer choices
foundation, frame, interior systems, roof
carpentry, masonry, plumbing, electrical
design, site prep, construction, turnover
define problem, define asis define tobe implement