Question: Assuming the process is in control and given n=4, and Upper Specification Limit of 13 minutes for order completion, and X-bar bar = 12.22, R-bar

Assuming the process is in control and given n=4, and Upper Specification Limit of 13 minutes for order completion, and X-bar bar = 12.22, R-bar = .4. What is the CPU for this process?

A..6552

B..7438

C..3452

D.1.338

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!