Question: Assuming the process is in control and given n=4, and Upper Specification Limit of 13 minutes for order completion, and X-bar bar = 12.22, R-bar
Assuming the process is in control and given n=4, and Upper Specification Limit of 13 minutes for order completion, and X-bar bar = 12.22, R-bar = .4. What is the CPU for this process?
A..6552
B..7438
C..3452
D.1.338