Question: At this point in time a work package is 6 0 % done and $ 1 0 0 , 0 0 0 was budgeted for
At this point in time a work package is done and $ was budgeted for it AND it should be complete. Then O a schedule variance BCWP BCWS is $
O b the work package is ahead of schedule
c None of these alternatives is correct.
O d the work package is over budget
O e schedule variance is $