Question: At this point in time a work package is 6 0 % done and $ 1 0 0 , 0 0 0 was budgeted for

At this point in time a work package is 60% done and $100,000 was budgeted for it, AND it should be 80% complete. Then O a. schedule variance (= BCWP - BCWS) is -$10,000
O b. the work package is ahead of schedule
c. None of these alternatives is correct.
O d. the work package is over budget
O e. schedule variance is -$20,000