Question: ates Corp. started a construction job with a total contract price of $7,000,000. The job was completed on December 15, 2017. Additional data are as
ates Corp. started a construction job with a total contract price of $7,000,000. The job was completed on December 15, 2017. Additional data are as follows: 2011 Actual costs incurred during the year Estimated remaining costs Billed to customer Received from customer $2,700,000 $3,400,000 3,300,000 2,400,000 4,600,000 2,00000 4,300,000 You MUST eyplain allyur answers to receve credit