Question: a.The project completion time is -------, with a normal cost of --------. * b .To crash the project by 1 day we choose activity _______

a.The project completion time is -------, with a normal cost of --------. * b .To crash the project by 1 day we choose activity _______ at an additional crashing cost of __________ * c.The new "project cost" is equal to * d .To crash the project by a forth day we choose ________ at an additional cost of * e.Crashing the project by 4 days results in
Consider the following scenario: Times are given in "days" Activity Predecessor Normal Cost ($) Crashing cost ($) Normal Time (days) 10 Crashing Time (days) 8 A $250.00 $400.00 B 7 5 $230.00 $300.00 , 9 7 $150.00 $380.00 D 6 4 $400.00 $500.00 E B 7 6 $325.00 $450.00 F D, E 2 1 $400.00 $490.00Step by Step Solution