Question: Atheel is sitting in his office, trying to develop a realistic project schedule. He examines the scheduling information in his project charter and milestone list,

Atheel is sitting in his office, trying to develop a realistic project schedule. He examines the scheduling information in his project charter and milestone list, then works with his team to create a more detailed schedule, before announcing to all project participants that the schedule has been set. What did Atheel forget to do? a He forgot to crash the schedule. b He forgot to fast track the schedule. c He forgot to get the approval of his project's stakeholders. d He didn't forget to do anything in developing the schedule