Question: awrence is the project manager for a railroad construction project. Her sponsor has asked her for a forecast for the cost of project completion. The

awrence is the project manager for a railroad construction project. Her sponsor has asked her for a forecast for the cost of project completion. The project has a total budget of $80,000 and CPI of .95. The project has spent $25,000 of its budget so far.
a) How much more money does she plan to spend on the project? (3 marks)
b) Will her project be over or under budget? Explain your answer. (4 marks)