Question: B 1 . Using the following table, do these tasks [ 2 0 points possible ] : a . Correctly & legibly draw and

B1. Using the following table, do these tasks [20 points possible]:
a. Correctly \& legibly draw and label the network diagram including process times
(Deduct 2 pts for each missing/incorrect: arrows, ovals, activity names, process times)
b. Complete the table of ES, EF, LS, and LFs [deduct \(2\mathrm{pts}/\mathrm{error}\)]
c. Identify the critical path or paths [deduct 8 points if incorrect]
\[
\mathrm{CP}(\mathrm{~s})
\]
 B1. Using the following table, do these tasks [20 points possible]:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!