Question: b 19 points A time study was conducted on a job. The observed times for 4 cycles (in minutes), and performance ratings, are listed below.

b
b 19 points A time study was conducted on a job.
19 points A time study was conducted on a job. The observed times for 4 cycles (in minutes), and performance ratings, are listed below. The allowance factor for the job is 0.16. Element Observation 1 Observation 2 Observation 3 Observation 4 Performance Rating A 23.1 21.0 224 210 104 Find the average cycle time for this job, also called the "Observed Time". (Provide your answer rounded to 1 decimal. Example --> 55.1) Type your

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!