Question: B 3 . Using the following table, do these tasks [ 4 5 points possible ] : a . Complete the table of ES ,

B3. Using the following table, do these tasks [45 points possible]:
a. Complete the table of ES, EF, LS, and LFs [deduct 2 ptslerror]
b. Identify the critical path or paths [deduct 10 points if incorreot]
c. If I wish to save 1 day. which activity would lcrash and how much more would it oost? [deduct 10 pts]
d. If w wish to save 2 days, which activity(ies) would l crash and how much more would it oost? [deduot 10 pts]
\table[[,Normal,Crash,,,],[Aotivity,Time (daya),Cost (s),Time (day),Cost (s),,,],[A,6,30,3,40,,,],[B,3,20,1,55,,,],[C,8,15,6,40,,,],[D,7,25,3,70,,,],[E,9,5,7,35,,,],[F,4,10,2,30,,,],[G,5,40,4,50,,,]]
\table[[,,Activity,],[,A,B,C,D,E,F,G
 B3. Using the following table, do these tasks [45 points possible]:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!