Question: Based on the following table, a) Draw the network for supposed processes b) Calculate ES, EF, LS, LF c) Calculate the project duration Activity Description
Based on the following table,
a) Draw the network for supposed processes
b) Calculate ES, EF, LS, LF
c) Calculate the project duration
| Activity | Description | Predecessors | Time (days) |
| A | initial market evaluations | - | 2 |
| B | R&D | A | 3 |
| C | Supply of production materials and equipment | A,B | 2 |
| D | scale up | C | 2 |
| E | obtaining legal permits | D | 5 |
| F | launch to market | D, E | 4 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
