Question: Based on the following table, a) Draw the network for supposed processes b) Calculate ES, EF, LS, LF for each node c) Calculate the project

Based on the following table, a) Draw the network

Based on the following table, a) Draw the network for supposed processes b) Calculate ES, EF, LS, LF for each node c) Calculate the project duration Activity A Predecessors Time (days) 2 Description initial market evaluations R&D B 2 C scale up A , 3 D C 4 obtaining legal permits launch to market Final evaluation E 3 CD E F 5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock