Question: B A 5 B 2 3 Consider the following development project (time given in days): Activity Predecessors Duration (Days) Slack A 3 B 4 3

B A 5 B 2 3 Consider the following development

B A 5 B 2 3 Consider the following development project (time given in days): Activity Predecessors Duration (Days) Slack A 3 B 4 3 D 2 E 1 F G H B 11 J DE 3 F,G L 4 M JH 4 Answer the following quesions: a) (5 pts) Draw the network. b) (1 pt) Find the critical path and critical time. c) (3 pts) Find the ES, EF, LS and LF times for each activity. d) (1 pt) Can the project be completed in 13 days? Support your response. 1 K 1