Question: B, B, Determine the critical path ? and the project duration is ___ days C, Calculate the slack for each activity The following information is

B, B, Determine the critical path ? and the project duration is ___ days
C, Calculate the slack for each activity
The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel: Immediate Predecessor(s) Activity Activity Time (days) 7 B 4 A C 3 A . D 3 E 4 D 2 F G 8 E a. Choose the correct network diagram for this project OA OB Start Finish Start Finish OA OB Start Finish Start Finish O C. OD Start Finish Start FinishStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
