Question: QUESTION 4 The table below gives the duration estimates in days for a construction projection. Predecessor Optimistic Pessimistic 7 2 1 6 Activity A B

QUESTION 4 The table below gives the duration

QUESTION 4 The table below gives the duration estimates in days for a construction projection. Predecessor Optimistic Pessimistic 7 2 1 6 Activity A B D E F G H 8 20 Most Likely 4 3 5 11 5 9 10 5 A A B E, F D G H,J IK 7 3 9 2 6 5 3 4 6 3 7 - 7 20 22 12 9 13 6 23 J 9 4 10 4.1 Determine the expected completion time for each activity. Round off answers to the nearest whole number. 4.2 Determine the critical path for the project by calculating the slack for each activity