Question: b Consider the table below. All duration estimates are in days. Use Activity-On-Node AON notation. Begin with Activity A as Oct 6 start date (expected
b
Consider the table below. All duration estimates are in days. Use Activity-On-Node AON notation. Begin with Activity A as Oct 6 start date (expected time is in days). Activity Expected Time Immediate Predecessors . 3 B 4. C 4 A D 5 A E 2 A F 3 C 2 B, E Io. 1 C, D, E 1 6 G H J 3 - K 5 L 2 K a. Create an AON diagram. b. List ALL the tasks in the critical path(s)? c. What is the earliest expected completion time (in days) for the project? d. What is the latest possible completion time for task H