Question: Consider the table below. All duration estimates are in days. Use Activity - On - Node AON notation. Begin with Activity A as Jan 6
Consider the table below. All duration estimates are in days. Use ActivityOnNode AON notation. Begin with Activity A as Jan start date expected time is in days
Activity Expected Time Immediate Predecessors
A
B
C A
D A
E A
F C
G B E
H C D E
I G H
J
K I
L K
a Create an AON diagram ID: Activity, startfinish dates, duration
b List ALL the activities in the critical paths
c What is the earliest expected completion time in days for the project?
d What is the earliest possible completion time for task I?