Question: Consider the table below. All duration estimates are in days. Use Activity - On - Node AON notation. Begin with Activity A as Jan 6

Consider the table below. All duration estimates are in days. Use Activity-On-Node AON notation. Begin with Activity A as Jan 6,2024 start date (expected time is in days).
Activity Expected Time Immediate Predecessors
A 3---
B 4---
C 4 A
D 5 A
E 2 A
F 3 C
G 5 B, E
H 1 C, D, E
I 6 G, H
J 3---
K 5 I
L 2 K
a. Create an AON diagram (ID: Activity, start/finish dates, duration).
b. List ALL the activities in the critical path(s)?
c. What is the earliest expected completion time (in days) for the project?
d. What is the earliest possible completion time for task I?
 Consider the table below. All duration estimates are in days. Use

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!